Façade renovation of the former Hotel Meyerhof, Hospental UR

Item

Hotel / Restaurant

Implementation

2021

Type

Conversion / Restoration

Location

6493 Hospental

Information

The old façade base coat was removed down to the quarry-stone wall, then completely rebuilt as follows (including allowing for appropriate drying times): Fixit 493 Mineral-based Undercoat Stabilizer was first sprayed onto the quarry-stone wall, then a 6 – 8 cm thick layer of Fixit 222 High Performance Insulating Render applied with reinforcing mesh, attached with Fixit 223 Special Embedding Mortar, embedded over the whole surface. Fixit 475 Primer for Mineral-Based Final Rendering was applied as an undercoat over the entire façade. The large white areas were covered twice with 0.5mm coats of Fixit 777 Fine Extra White Render. The smaller grey areas were covered with a mixture of Fixit 205 (base coat with hydraulic lime) and 208 (basic mixture for restauration work) to create a Tyrolean render. This was applied with a hand-operated plaster spreader/flicker. Finally the façade was given two coats of mineral-based paint.

Used products

Fixit 208

Basic mixture for restoration work

Fixit 222

Aerogel High Performance Insulating Plaster

Fixit 223

Special Embedding Mortar

Fixit 211

Roughcast mortar with adhesive agent

Fixit 475

Primer for mineral-based final renderings

Involved companies

Architect

HTS Architekten + Partner AG, 6460 Altdorf

Processor

GB Gipsbau AG, 6060 Sarnen

Builder

Gamma AG Immobilien, 6467 Schattdorf